Prior to beginning design of the project, the Diocese and Kisco believed it was very important to meet with adjacent homeowners to discuss the vision for the project and to seek input.  A series of meetings and workshops were held over a two year period.  Hundreds of residents attended these meetings and provided valuable input on site issues, concerns and questions.  Most of these comments are summarized in the FAQ section tab.  Additional input will be gathered through the coming public review process let by the County of Orange (see upcoming meetings tab).

    2007
       
    Feb - March Meet with local leaders - NTAC/FCA
    Mar 22 Neighborhood Workshop (adjacent homes) - Click for more info
    Aug 14 & 16 Neighborhood Workshop (adjacent homes) - Click for more info
    Nov 13 & 15 Neighborhood Workshop (surrounding neighborhood) - Click for more info
    Nov 19 NTAC informal hearing
     
    2008  
       
    Mar 11 Pre-submittal package to County Meetings with staff
    June RMV proposed Senior Living Fac Ordinance
    Jun 12 Re-submittal to County Staff
    Aug - Sept Meet with local leaders - NTAC members
    Aug 12 Diocese application deemed complete
  Dec 3 & 4 Neighborhood Workshop - Click for more info
    Dec 20 Senior Living Facility Ordinance Adopted
       
    2009
       
    Jan 7 Neighborhood Workshop (east of Newport Ave.) - Click for more info
    August 11 EIR Scoping Meeting *
    TBD Distribute Draft EIR *
       
       
*   Anticipated.
     
    Community Outreach & information Gathering
     
    Conceptual Plan Presentations & Refinements
     
    Discretionary Approval Process